Current Construction Happenings 12/19/2025:
Current Project Highlights:
  • Full Site Overlot Grading Complete
  • Site Sanitary 90% Complete
  • Water Loop and Hydrants Complete
  • Foundations in Area D (Athletic Wing) 50% Complete
  • Masonry Starter Coarse at ES and MS Gym Complete
  • Foundations Started in Area E ( Elementary Classroom Wing)
     
4 Week Look Ahead:
  • Run Fire and Domestic Water Into the Building
  • Back Fill Area D (Athletic Wing) Foundations
  • Install Shallow Underground Utilities in Area D (Plumbing and Electrical)
  • Pour Concrete Slabs in ES and MS Gyms
  • Prep and Pour Foundations in Area E ( Elementary Classroom Wing)
  • Start Backfill of Foundations in Area E
 
Current Construction Happenings 11/07/2025:
  • Earthwork:
    • Approximately 115,000 cubic yards of dirt will be moved onsite. For reference, that’s about 3.1 million cubic feet—enough to cover a football field (including end zones) 54 feet deep, or roughly 7,700 dump truck loads (at 15 CY per load).
  • Utilities:
    • Around 12,000 linear feet of water, sewer, and storm piping will be installed onsite. That’s about 2.3 miles in total length, or roughly 40 football fields placed end-to-end.
    • 1st Ave utility work is tracking to be complete Nov/Dec and road open to public mid-Dec.  
  • Building:
    • Excavating for building foundation is scheduled to start this month with the first concrete pour at the end of November.
    • Structural Concrete Masonry Units will start February and run through May. This will allow for structural steel installation to start in May.